MANDATORY SUBMITTAL
OF
ENERGY
CODE COMPLIANCE DOCUMENTS
FEBRUARY 23, 2009
·
Effective March 16, 2009, the Energy Code Compliance
Documentation, when required, shall be submitted with the Final
Submittal instead of the Preliminary Submittal. Final Submittals that do
not include the Energy Code Compliance Documentation shall be considered
incomplete and will not be approved.
·
For projects where the Energy Code Compliance
Documentation was submitted with the Schematic or Preliminary Submittal
prior to March 16, 2009 and the Final Submittal will be submitted after
March 16, 2009, the Energy Code Compliance Documentation shall be
resubmitted with the Final Submittal.
·
For projects where the Revised Final Submittal will be
submitted after March 16, 2009 but the Final Submittal was received
prior to March 16, 2009, the Energy Code Compliance Documentation will
not be required for approval unless previously noted on the Final
Project Comment Letter or the design has been modified to the extent
that the previously submitted Energy Code Compliance Documentation is no
longer valid.
·
Per the Building Commission’s Administrative Rule
170-X-2-.04 (2), the State Energy Code only applies to buildings
constructed or remodeled with state appropriated funds or funds from any
other instrumentality of the state.
|