|
A. APPLICABILITY of CHAPTER
This chapter sets forth requirements and procedures
for administering construction contracts of projects supervised and
administered by the Technical Staff. The types of projects to which this
chapter applies includes projects of:
- State Agencies & Departments
- Public School & College Authority (PSCA)
- Alabama Building Renovation Finance Authority (ABRFA)
- Alabama Corrections Institution Finance Authority (ACIFA).
- Alabama Mental Health Finance Authority (AMHFA)
- Other "authorities" established by legislative acts to fund
specific construction or improvement programs and which are assigned
by the legislative act to the ABC for administration and supervision.
B. INTRODUCTION
The Contract Administration Division of the Technical
Staff supervises the administration of construction contracts through
the ABC’s uniform documents and standard forms. All documents submitted
for a project are checked for completeness, accuracy, and the presence
of any prerequisite documentation prior to receiving approval of the
Technical Staff. Payments by State Agencies, Departments, the PSCA and
other "authorities" to contractors, suppliers, and consultants must be
approved by the Technical Staff and are subject to disapproval in the
absence of compliance with prerequisite procedures and requirements.
BEFORE PROCEEDING WITH THE REQUIREMENTS OF THIS
CHAPTER , it is recommended that the reader
first refer to the "Summary of ABC Requirements by Project Type" in the
Introduction to this Manual and then to the project appendix indicated
in the "Summary" to obtain a general understanding of the ABC's
authority, requirements, and procedures applicable to the proposed
project.
This Manual only addresses requirements and
procedures of the ABC, before proceeding with preparation of bid
documents or submittals to the ABC the design professional should
determine whether sources of project funding (such as federal funding)
or regulations peculiar to the Awarding Authority may require
modification or supplementation of the ABC requirements and procedures.
If it is determined that such modification or supplementation will be
necessary, contact the Technical Staff for guidance as to the
appropriate method.
C. DOCUMENT REQUIREMENTS
1. USE OF ABC UNIFORM DOCUMENTS AND STANDARD FORMS
ABC uniform documents and standard forms contained in
Appendix B and Appendix C are to be utilized for all phases of
construction contracting and administration. Appendix B contains
standard forms to be utilized by the design professional in performing
his or her administrative services. Appendix C contains uniform
documents and standard forms which are to be bound into the project
manual establishing the project’s advertisement, bidding instructions,
contractual documents, and administrative forms. Chapter 5 discusses the
acceptable methods of reproducing, altering, and modifying these
documents.
2. USE OF BC PROJECT NUMBER
In the ABC's document management system all documents
relative to a "project" are stored under a seven-digit Building
Commission Project Number [Example: BC#2001567]. All new projects
are assigned a BC Project Number and the design professional is advised
of the number. All project related correspondence and documents
subsequently submitted to the ABC must clearly display the BC
Project Number. A space is provided for this number on all uniform
documents and standard forms.
The scope of a "project" is the scope of the Work
covered by the O/A Agreement. Therefore, the BC Project Number assigned
to the O/A Agreement will also cover all resulting bid packages
and construction contracts. Frequently, an O/A Agreement will involve
improvements to be made at several different schools within a school
system, in such cases each bid package and construction contract
performed will be recorded and tracked under the BC Project Number
assigned to the O/A Agreement. If the scope of an O/A Agreement is
expanded by Amendment resulting in additional bid packages and
construction contracts, the additional bid packages and contracts will
be recorded and tracked under the BC Project Number of the original O/A
Agreement.
3. QUALITY OF DOCUMENTS SUBMITTED TO THE ABC
The ABC utilizes a document management system which
is capable of scanning, storing, retrieving, and faxing documents. To
produce an acceptable quality in documents retrieved from this system,
the following is required of documents submitted to the ABC:
a. Submit original documents - no carbon copies.
b. Do not highlight text. Highlighted text does
not produce a good scanned image.
c. Preferably, submit only letter size (8½ X 11)
documents.
d. Preferably, send only one-sided documents.
4. QUANTITY OF DOCUMENTS TO BE SUBMITTED
a. Plans and Specifications: Only one (1)
set of plans and specifications is to be submitted for plan review under
Chapter 3.
b. Contractual Documents: Six (6) complete
sets of contractual documents bearing originals of all signatures,
notarizations, and attachments are to be submitted to the ABC.
"Contractual Documents" include: O/A Agreements and Amendments,
Construction Contracts with Bonds, Change Orders and Modifications to
Construction Contracts, and any other agreements or documents that
require the signature of the Governor as an approving or contracting
party.
c. Other Documents: In general, six (6)
copies of all other documents requiring the approval of the ABC are to
be submitted to the ABC. Such documents include Statements for Services,
Applications for Payment, invoices, etc. Exceptions to this rule are
noted elsewhere in this Chapter.
d. Contractor's Submittal Data and Shop Drawings:
Copies of the contractor's submittal data and shop drawings ARE NOT
TO BE SUBMITTED TO THE ABC.
D. PREPARATION and EXECUTION of the
CONSTRUCTION CONTRACT
The bidder to whom a Construction Contract is awarded
must execute and return the contract, with (1) performance and payment
bonds, executed by a surety company duly authorized and qualified to
make such bonds in Alabama, and (2) evidence of insurance as required by
the bid documents within the period specified or, if no period is
specified, within 15 days after the contract and bond forms are
presented to the bidder. Under extenuating circumstances the Awarding
Authority may extend this period up to five days. (§39-2-8, Public Works
Law) A longer period than 15 days for the return of the executed
contract, bonds, and evidence of insurance may be provided for in the
Bid Documents.
It is the responsibility of the design professional
to prepare the Construction Contract and deliver it, with bond forms, to
the contractor for acceptance and execution. The following ABC standard
contract and bond forms are to be utilized:
ABC Form C - 5: Construction Contract
ABC Form C - 6: Performance Bond
ABC Form C - 7: Payment Bond
These forms are contained in Appendix C and are
available through the internet from the ABC’s Web site [ can be
completed "on line". Six (6) copies of the contract and bonds, bearing
original signatures of the contractor, Awarding Authority, and surety,
are to be submitted to the Technical Staff for approval, processing, and
distribution.
1. CHECKLIST - PREPARATION and APPROVAL of
CONSTRUCTION CONTRACTS and BONDS, ABC Form B-7
ABC Form B-7, "Checklist for
Preparation/Approval of Contract and Bonds", is contained in Appendix B.
The design professional should use this Checklist when preparing the
contract for acceptance and signature by the contractor. When the
contractor returns the signed contract with bonds, the design
professional should use the Checklist in reviewing and approving the
documents for forwarding to the Awarding Authority. A copy of the
Certified Bid Tabulation must also accompany the
executed contract and bonds. It is of the utmost importance that
figures shown on the bid tabulation correspond with those shown on the
Construction Contract as this is part of the verification of the
competitive bid process.
2. EXECUTION AND PROCESSING OF THE CONTRACT
Appendixes A-1, A-2, and A-3 describe required
signatures and typical routing and processing of Construction Contracts
for PSCA, State Agency, and Postsecondary Education projects. Processing
of Construction Contracts for special construction projects or programs
are to be developed consistent with the Legislature's authorizations of
such projects or programs. The Technical Staff will make final
distribution of the fully executed and approved contract and bonds to
the contractor, Awarding Authority, design professional, and any other
required party.
3. PROJECT DATA FORM, ABC Form B-9
After the Construction Contract
has been executed, the design professional shall complete and submit ABC
Form B - 9, Project Data Form, to the ABC's Contract
Administrator. This form is contained in Appendix B and is available
through the internet from the ABC’s Web site [ can be completed "on
line".
4. BIDDER’S FAILURE TO EXECUTE CONTRACT AND BONDS
If the bidder to whom the contract is awarded fails
or refuses to sign the contract, to furnish the required bonds, or to
provide evidence of required insurance within the specified period of
time, the Awarding Authority may award the contract to the second lowest
responsible and responsive bidder. If the second lowest responsible and
responsive bidder also fails or refuses to contract, to furnish the
required bonds, or to provide evidence of required insurance within the
specified time, the Awarding Authority may award the contract to the
third lowest responsible and responsive bidder. Failure or refusal to
return the executed contract and bonds within the specified time is
grounds for forfeiting all or part of the proposal guaranty. (§§ 39-2-6
& 11, Public Works Law)
5. AWARDING AUTHORITY’S FAILURE TO COMPLETE EXECUTION
OF CONTRACT
The Awarding Authority is to approve the bonds and
evidence of insurance and complete execution of the contract within 20
days of receipt of the documents, unless the contractor agrees in
writing to a longer period of time. A Notice To Proceed is to be issued
(by the Technical Staff) within fifteen days after final execution of
the contract, and execution by the Governor if his or her signature on
the contract is required by law, unless the contractor agrees in writing
to a longer period of time. Failure by the Awarding Authority to
complete execution of the contract or issue a Notice To Proceed within
these time periods, or agreed extended periods, shall be just cause for
the withdrawal of the contractor’s bid and contract without forfeiture
of bid security. (§§ 39-2-9, 10, & 11, Public Works Law)
E. NOTICE TO PROCEED
The Notice to Proceed (NTP) with the work will be
issued to the contractor by the Technical Staff. Final distribution of
the fully executed and approved contract and bonds is made with the NTP.
The NTP will be issued after verification that the project’s plans and
specifications received final approval of the review staff. If it is
found that the plans and specifications do not have final approval
status due to the absence of response to review comments or untimely
submittal, the issuance of an NTP and distribution of the contract will
be held in abeyance pending resolution of design issues by the design
professional.
The NTP will state both the date upon which the Work
may commence and the date upon which the Work is to be completed. With
the NTP the Technical Staff will also provide the contractor with
appropriate standard forms and a "Contractor’s Checklist" identifying
submittal items required by the ABC.
F. INITIAL DOCUMENTS REQUIRED from CONTRACTOR
Upon receipt of the contract and Notice to Proceed,
the contractor will be required to submit the following documents to the
Technical Staff through the design professional.
1. SCHEDULE OF VALUES
The General Conditions require the
submission of the contractor’s proposed Schedule of Values within 10
days after receipt of the Notice to Proceed. The Schedule of Values is
to be a breakdown of the contract price which will be the basis for
approving the contractor's monthly progress payments. The detail and
format of the Schedule of Values is to be determined by the Awarding
Authority and design professional, the criteria dictated by the ABC is
that it be on 8½ × 11 inch paper so that it is compatible with our
electronic filing system.
The Schedule of Values submitted by the contractor
may be rejected if it is apparent that overhead, profit, and costs have
been disproportionately assigned to the earlier, "front-end" elements of
work or if it does not otherwise reflect a reasonable breakdown of
values. The contractor's home-office overhead and profit are to be
proportionately distributed throughout the various elements of the
Schedule of Values. The contractor's on-site supervision and other
on-site and direct overhead costs may be included in a "General
Requirements" category. If a "General Requirements" category is
utilized, an understanding should be reached among the contractor,
design professional, and Awarding Authority as to what costs are
included and on what basis they are to be paid. The contractor's
"up-front" costs for bond and insurance premiums (other than payroll
insurance) and mobilization may be paid in the first pay estimate, but
typically should not exceed 2 to 3% of the contract amount. Other costs,
such as supervision, temporary facilities, layout and engineering, and
quality control testing, are costs that are incurred throughout the life
of the project and should be paid as earned on a monthly basis.
The ABC recommends establishing line items in the
Schedule of Values for such requirements as "as-built" drawings,
instruction of maintenance personnel, and Operating & Maintenance
Manuals. Such line items emphasize these requirements and improve the
likelihood of timely accomplishment of these typically belated
administrative obligations. Reasonable values for such items may be
predetermined by the design professional and Awarding Authority and
stipulated in the bid/contract documents.
2. PROGRESS SCHEDULE - ABC Form C - 11
On all projects exceeding 60 days duration, the
contractor shall prepare and submit for approval by the design
professional a reasonable schedule showing the order in which the
contractor proposes to carry out the work; refer to "Progress Schedule"
in the General Conditions. ABC Form C-11, Progress Schedule and Report,
or a similar format, is to be utilized for this purpose on all projects
and is to be updated monthly and submitted to the Technical Staff with
each pay request. ABC Form C-11 provides the minimum bar chart
information needed by the Technical Staff for monitoring purposes, but
more scheduling detail is acceptable. On larger, more complex projects,
CPM or other more detailed scheduling methods should be specified, but
only ABC Form C-11, or a similar format, is to be updated and submitted
to the Technical Staff monthly.
3. LIST OF SUBCONTRACTORS
The General Conditions require the names of
subcontractors to be submitted concurrently with the execution of the
contract. This list should be inclusive of any additional subcontractors
that were not required to be named in the bid process.
G. PAYMENTS to CONTRACTORS
1. MONTHLY PROGRESS PAYMENTS
The contractor is to be paid on a monthly basis
commensurate with the progress of the work. ABC Form C-10, Application
and Certificate for Payment (with the Contractor’s updated Schedule of
Values attached), is to be used for requesting payments. In preparing
estimates for progress payments, materials suitably stored on site,
materials suitably stored and insured off-site, and preparatory work may
be taken into consideration. If materials stored off site are to be
considered in progress payments, General Conditions Article 29, Progress
Payments, provides prerequisites for such payments.
Any amount to be paid to a contractor must be
approved by the design professional and Awarding Authority. If the
design professional or Awarding Authority approves an amount that is
less than the amount requested by the contractor, the contractor is to
be notified in writing of the amount approved and the reason for not
approving the amount requested.
Appendixes A-1, A-2, and A-3 describe typical
approvals, routing, and processing of applications for payment for PSCA,
State Agency, and Postsecondary Education projects. Processing of
applications for payment for special construction projects or programs
are to be developed consistent with the Legislature's authorizations of
such projects or programs.
2. RETAINAGE
"Retainage" is defined as the money earned and,
therefore, belonging to the contractor which has been retained by the
Awarding Authority conditioned on final completion and acceptance of all
work required by the contract. Retainage shall not be relied upon to
cover or off-set the cost of uncompleted or uncorrected Work.
In making monthly progress payments to the
contractor, the Awarding Authority is to retain 5% of the estimated
value of the completed work, materials stored on site, and materials
stored and insured off-site and after 50% completion is accomplished no
further retainage is to be withheld. Retainage must be withheld until
final completion and acceptance of the work covered by the contract.
3. PAYMENTS WITHHELD
In addition to retainage, the General Conditions to
the Contract provide that an Awarding Authority may withhold payments
from a contractor to the extent necessary to protect the Awarding
Authority from loss due to causes listed in General Conditions Article
31, Payments Withheld.
4. FINAL PAYMENT
Approval of an Application for Final Payment by the
design professional and Awarding Authority represents that all
requirements in the field, such as completion of "punch list" items,
have been completed to their satisfaction. Such approval should not be
withheld for items that are covered by warranties. Upon verification
that all prerequisite requirements and procedures have been completed,
the ABC will approve the Application for Final Payment and forward it
for issuance of payment.
ABC Form B-13, FINAL PAYMENT CHECKLIST & TRANSMITTAL,
contained in Appendix B, is to be completed by the design professional
and used to transmit the contractor's Application for Final Payment.
This form is intended as a tool by which the design professional,
Awarding Authority, and ABC can quickly verify that all administrative
requirements have been accomplished for approval of Final Payment.
H. CHANGE ORDERS
Actions arising from provisions of the General
Conditions of the Contract can necessitate modification of the
Construction Contract by Contract Change Orders. Five articles which
specifically pertain to Change Order action are:
Article18, DEDUCTIONS FOR UNCORRECTED WORK:
Provides that, at the Awarding Authority's discretion, work at variance
with the contract requirements may remain in place and uncorrected if an
equitable deduction from the contract is offered by the contractor and
approved by the Awarding Authority.
Article 19, CHANGES IN THE WORK: Addresses
changes that may be requested by the Awarding Authority. It establishes
that the Awarding Authority may make changes within the general scope of
the work, establishes change order procedures, and provides three
methods from which the Awarding Authority may choose to determine the
monetary value to be added to, or deducted from, the contract amount for
changes.
Article 20, CLAIMS FOR
EXTRA COST OR EXTRA WORK: Establishes conditions under which a
contractor's claim(s) for extra cost or extra work can be considered
under Article 19 or pursued under Article 24, Resolution of Claims and
Disputes.
Article 21, DIFFERING SITE CONDITIONS: Defines
"Differing Sites Conditions", establishes that the contract can be
adjusted for Differing Site Conditions under Article 19, and establishes
procedures to be followed if Differing Site Conditions are encountered.
Article 23, DELAYS: Provides for extending the
Contract Time for certain conditions beyond the contractor's control,
such as strikes, fires, unusually adverse weather, etc.
When it is necessary to modify the Contract, the
provisions of the above articles regarding notifications and detailed
cost proposals are to be enforced and the following procedures followed:
1. CHANGE ORDER JUSTIFICATION, ABC Form B-11
Changes In The Work stipulates that the Awarding
Authority may make changes "within the general scope" of the
Contract, which limits the types of changes that can be made. More
importantly, the requirements of the state's Competitive Bid Laws may
limit the extent to which work may be awarded through change order
action as opposed to award through the competitive bid process. In that
the Competitive Bid Laws do not specifically address construction
contract change orders, there are not clear-cut rules by which to
measure their limitations. Additionally, court rulings and opinions
issued by the Office of the Attorney General have maintained that public
officials should be allowed discretion in administering the Competitive
Bid Laws as long as they are acting in good faith and in the public
interest. Therefore, when considering making changes to the contract,
the design professional and the Awarding Authority should be cognizant
of the potential of conflict with the Competitive Bid Laws.
Determination of legality of change orders rests with the Awarding
Authority and its legal advisor. In an opinion of June 15, 1979, the
Office of the Attorney General offered guidelines for making such
determinations.
ABC Form B-11, Change Order Justification, is
contained in Appendix B and provides a means through which the Awarding
Authority and design professional consider the AG's guidelines and the
intent of the Competitive Bid Laws. A Change Order Justification is to
be submitted with each proposed Change Order, except for Change Orders
which only address extensions of time. The form is to be prepared by the
design professional and signed by the design professional and the
Awarding Authority. It is highly recommended that the Awarding
Authority's legal advisor review each proposed Change Order and confirm
justification of change order action by signing the respective Change
Order Justifications.
2. CONTRACT CHANGE ORDER, ABC Form C-12
CHANGE ORDER CHECKLIST, ABC Form B-12
ABC Form C-12, Contract Change Order,
contained in Appendix C, must be utilized in making changes to the
Construction Contract. The form is to be prepared by the design
professional. The form is self-explanatory and must be completed in its
entirety. Typically required signatures for PSCA, State Agency, and
Postsecondary Education projects are shown in Appendixes A-1, A-2, and
A-3 respectively. CONSENT OF SURETY, with current Power of
Attorney for the individual signing for the surety, IS REQUIRED FOR ALL
CHANGE ORDERS, except Change Orders addressing only extensions of time.
ABC Form B-12, Change Order Checklist, is provided in Appendix B
as a simple reference to be followed to assure that all required aspects
of change order documents are provided.
3. CHANGE ORDER PROCESSING
Appendixes A-1, A-2, and A-3 describe typical routing
and processing of Contract Change Orders for PSCA, State Agency, and
Postsecondary Education projects. Processing of Contract Change Orders
for special construction projects or programs are to be developed
consistent with the Legislature's authorizations of such projects or
programs.
4. ABC APPROVAL OF CONTRACT CHANGE ORDERS
The ABC's approval of a Contract Change Order will be
based upon the following reviews:
a. Code Review: Each Contract Change Order
will be reviewed by the Plan Review Division giving consideration to
changes in the work which may affect code compliance of the originally
approved plans and specifications. Clarification from the design
professional may be requested for changes suspected of affecting the
building's code compliance and for which inadequate information is
provided in the change order documents.
b. Technical and Procedural Review: Each
Contract Change Order will be reviewed by the Contract Administration
Division checking for completeness, accuracy, and compliance with
contractual and procedural requirements. Conspicuous or apparent pricing
errors or variances from contract provisions will be questioned.
I. CLAIMS and DISPUTES
The General Conditions of
the Contract provide for the Director’s final, binding, and conclusive
resolution of claims and disputes that may arise between the contractor
and Awarding Authority in state-funded contracts. (Final resolution of
locally-funded contracts is not specifically defined unless Modified
General Conditions or Special Conditions address this matter.)
In the event that an issue does arise between the
contractor and the Awarding Authority, every effort should be made to
resolve the issue between them with the objective assistance of the
design professional. The General Conditions encourage, but do not
require, mediation as a means of settling disputes. Only when an impasse
to agreement or compromise is reached should an issue be submitted to
the Director for settlement. An issue may be submitted to the Director
upon written agreement by the contracting parties to do so. The form of
this agreement and the procedures to be followed for the resolution of
claims and disputes shall be prescribed by the Director.
J. SUBCONTRACTORS' and SUPPLIERS' CLAIMS of NONPAYMENT
Should a subcontractor or material supplier have a
valid claim of nonpayment by a contractor for work performed or
materials supplied on any public works project in Alabama, the
claimant’s source of remedy is the contractor's surety through the
Payment Bond.
Frequently, the subcontractor or supplier will serve
notice to the Awarding Authority or ABC of its claim of nonpayment. In
such cases, sub-section 39-1-1(b) of the Public Works Law requires the
entity receiving the notice to promptly furnish the claimant with a
certified copy of the Payment Bond and construction contract. It is
suggested that the claimant also be furnished with a copy of section
39-1-1.
Additionally, the following two articles of the
General Conditions of the Contract address actions that the Awarding
Authority may take in response or relative to claims of nonpayment:
PAYMENTS WITHHELD: Addresses the Awarding
Authority's right to withhold amounts from payments to the contractor to
cover the amount(s) of claimed nonpayment(s).
FINAL PAYMENT:
Addresses the Awarding Authority's right to require the contractor to
furnish releases of claims and/or other instruments evidencing
settlement of claims prior to Final Payment.
K. LIQUIDATED DAMAGES
Under Liquidated Damages,
the General Conditions of the Contract provides that "...unless
otherwise provided in the Contract Documents, a time charge of 6 percent
interest per annum on the total Contract Sum may be made against the
Contractor for the entire period after expiration of the Contract Time
that the Contractor fails to achieve Substantial Completion of the
Work,…If part of the Work is substantially completed within the Contract
Time and part is not, the stated charge for liquidated damages shall be
prorated to that portion of the Work that the Contractor fails to
substantially complete within the Contract Time." The rate or amount
of liquidated damages should be a reasonable, supportable forecast of
actual damages that the Awarding Authority is likely to incur due to
late completion of the project. If 6 percent interest is excessive
or inadequate, a supportable daily amount or percentage rate
should be stipulated in Modifications to the General Conditions. If
liquidated damages are not justifiable for a particular project they
should be deleted by Modifications to the General Conditions.
The time for completion of the work should be stated
in the Construction Contract and the date by which the work is to
be completed will be stated in the Notice to Proceed. The date by which
the work is to be completed may be extended by change order. Unless
otherwise provided in Modifications to the General Conditions or Special
Conditions, the Certificate of Substantial Completion (discussed in
Chapter 8) will establish the date upon which the work is deemed
"complete" relative to assessment of liquidated damages.
The amount of liquidated
damages is to be deducted from the Final Payment to the contractor. A
change order, even if unilateral, must be issued to the contract to
account for this deduction. If a severe time over-run is being
experienced, a sufficient amount should be withheld from the
contractor’s payment to cover the potential amount of liquidated
damages.
L. PROJECT CLOSEOUT
The closeout of a Construction Contract, or "Project
Closeout", is achieved upon the Awarding Authority's issuance of Final
Payment to the contractor. However, upon completion of the work in the
field, certain administrative requirements must be accomplished by the
contractor and the design professional must verify that other
contractual matters are finalized before Final Payment can be approved.
This section sets forth the minimum requirements that must be
accomplished before the Technical Staff can approve Final Payment.
The design professional should ascertain what additional requirements
may be imposed by the project funding source(s) or Awarding Authority.
1. CERTIFICATE OF SUBSTANTIAL COMPLETION
The Certificate(s) of Substantial Completion,
accounting for the completion of all areas and/or phases of the Work,
must be fully executed and forwarded to the Technical Staff. See Chapter
8 for further information.
2. ADVERTISEMENT OF COMPLETION
Under Final Payments, the General Conditions of the
Contract provide that the contractor must advertise completion of the
project for four successive weeks as a prerequisite to Final Payment.
The article stipulates how the advertisement must be published, or
posted, and what evidence of publication must be provided. This article
is consistent with the provisions of Public Works Law, Subsection
39-1-1(f) applying to projects of $50,000 or more in value. Final
payment cannot be made until thirty (30) days after this advertisement
requirement is completed.
For projects of less than $50,000 in value,
advertisement of completion, or posting of notice of completion, for one
week is required of the Awarding Authority. Final payment can be made at
any time after this requirement is completed. If the Construction
Contract is for less than $50,000 and the ABC’s General Conditions are
used, the Applications for Partial and Final Payments article should be
amended to be consistent with this provision of the Public Works Law.
ABC Form C-14, Form of Advertisement of Completion,
is contained in Appendix C. A copy of the actual advertisement and the
publisher's affidavit of publication is to be attached to each copy of
the contractor's Application for Final Payment. If any part of retainage
is to be released to the contractor prior to Final Payment, the
advertisement and affidavit are to be submitted with the Application for
Payment applicable to such release of retainage.
3. RELEASE OF CLAIMS
A release of claims or other instruments as described
in the General Conditions to the Contract may be required of the
contractor prior to Final Payment. If notices of claims have been given
by subcontractors or suppliers during the course of the project, the
contractor must furnish releases of claims from the claimants or other
instruments acceptable to the Awarding Authority.
A copy of each release of claims is to be attached to
each copy of the contractor's Application for Final Payment. If any part
of retainage is to be released to the contractor prior to Final Payment,
releases of claims are to be submitted with the Application for Payment
applicable to such release of retainage.
4. WARRANTIES
All specified warranties must be furnished to the
Awarding Authority by the contractor, with copies or evidence of same
provided to the Technical Staff as stated below. Regardless of when the
warranties are furnished to the Awarding Authority, these requirements
should be addressed to the Technical Staff at the time of submission of
the contractor's Application for Final Payment.
a. CONTRACTOR'S ONE-YEAR WARRANTY: Under
Guarantee of the Work, the General Conditions of the Contract provide
that the contractor guarantees the work for one year after completion.
The date upon which this warranty begins is established in the
Certificate of Substantial Completion. Unless provided otherwise in
Modifications to the General Conditions, the contractor is not required
to furnish this warranty in writing; however, it is recommended that the
contractor provide a letter which reconfirms this warranty and the dates
thereof. A copy of such letter should be forwarded to the Technical
Staff.
b. GENERAL CONTRACTOR'S 5-YEAR ROOF WARRANTY: ABC
Form C-9, General Contractor’s Roofing Guarantee, is contained in
Appendix C and is required to be included in the specifications of all
projects administered by the ABC and which involve roofing work. THIS
GUARANTEE IS BY THE GENERAL CONTRACTOR, not a subcontractor. Any other
roof warranties to be provided by the roofing manufacturer,
subcontractor, or general contractor are in addition to this guarantee.
This guarantee, bearing original signature of the general contractor, is
to be furnished to the Awarding Authority AND the Technical Staff
with the Certificate of Substantial Completion.
c. OTHER ROOFING WARRANTIES: If the contract
specifies any other roofing warranties to be provided by the
roofing manufacturer, subcontractor, or general contractor in addition
to the 5-year roof warranty, such warranties shall also be furnished to
the Awarding Authority AND Technical Staff with the Certificate of
Substantial Completion.
d. OTHER WARRANTIES: The Technical Staff need not
be furnished copies of other warranties specified in the contract;
however, the design professional is to notify the Technical Staff that
this requirement has been fulfilled.
5. AS-BUILT DRAWINGS
Verification must be given to the Technical Staff
that (contractor prepared) "as-built" drawings and specifications have
been provided to the Awarding Authority in accordance with contract
requirements.
6. OPERATING AND MAINTENANCE MANUALS
Verification must be given to the Technical Staff
that contractor prepared maintenance instructions and Operating &
Maintenance Manuals have been furnished to the Awarding Authority in
accordance with contract requirements.
7. RECONCILIATION OF CONTRACT TIME
If the date of substantial completion stated in the
Certificate(s) of Substantial Completion is later than the contract date
of completion stated in the Notice To Proceed, or as extended by change
orders, a time over-run exists which must be reconciled. This can be
done by: (1) executing a change order extending the contract time to the
date of substantial completion, (2) providing the Technical Staff with a
statement from the design professional and Awarding Authority explaining
that the over-run was justifiable or acceptable, or (3) assessing
liquidated damages commensurate with the over-run. If liquidated damages
are assessed, a change order (unilateral, if necessary) must account for
the amount of liquidated damages deducted from the contractor's final
payment.
M. OWNER’S OCCUPANCY and ASSUMED RESPONSIBILITIES
When the Awarding Authority (owner) takes possession
of, or occupies, the completed project, the owner must assume many
responsibilities previously performed by the contractor. Building
security, maintenance, utility services, and insurance become the
owner’s responsibility and the owner must be prepared to assume these
responsibilities on the date of substantial completion, unless some
other date is agreed upon with the contractor. This transfer of
responsibilities occurs on the date of substantial completion (or other
agreed date) regardless of whether the owner actually moves into the
building. If it is agreed by the contractor that any of these
responsibilities will transfer to the owner on a date subsequent to the
date of substantial completion, this agreement must be recorded in an
attachment to the Certificate of Substantial Completion.
Owners frequently occupy portions of a building or
move furnishings and equipment into a building prior to the date of
substantial completion. In such cases it is of extreme importance that
the owner consults with its insurance advisor to coordinate the owner’s
insurance coverage with that of the contractor.
|