|
A. APPLICABILITY of CHAPTER
This chapter defines required and recommended
procedures for the bid and award of contracts for projects supervised
and administered by the Technical Staff. The types of projects to which
this chapter applies includes projects of:
State Agencies & Departments
Postsecondary Education
Public School & College Authority (PSCA)
Alabama Building Renovation Finance
Authority (ABRFA)
Alabama Corrections Institution
Finance Authority (ACIFA).
Alabama Mental Health Finance
Authority (AMHFA)
Other "authorities" established by
legislative acts to fund specific construction or improvement programs
and which are assigned by the legislative act to the ABC for
administration and supervision.
B. ADVERTISEMENT for BIDS
Title 39, "Public Works Law", requires
the Awarding Authority to advertise for sealed bids once a week for
three weeks for public works projects in excess of $50,000.00. The
advertisement is to be published in a newspaper of general circulation
in the county or counties in which the project, or any part of the
project, is to be performed. If the project involves an estimated amount
in excess of $500,000.00, the Awarding Authority must also advertise for
sealed bids at least once in three newspapers of general circulation
throughout the state. Exceptions may be made in cases of emergencies
affecting public health, safety or convenience, so declared in writing
by the Awarding Authority, setting forth the nature of the danger
involved in any delay.
The advertisement is to be prepared and its
publication arranged for by the design professional. The published text
of the advertisement is to be bound in the project manual. Proof of
publication should be obtained from the newspaper(s) and retained for
submission with the contract to the Technical Staff. ABC Form C-1 is a
sample Advertisement for Bids containing language satisfying the
requirements of various state laws. The design professional should
closely follow the language and format of the sample while incorporating
project-specific information necessary to legally describe the
solicitation. Project-specific information in the advertisement should
include:
Brief description of the scope of
the work.
Where, in the Awarding Authority’s
offices, plans and specifications are on file for examination.
Procedure for obtaining plans and
specifications.
Time and place in which bids shall
be received and opened publicly.
Whether prequalification is required
and where all written prequalification information is available for
review (see Chapter 5, Section D.6 for prequalification procedures
required by the Public Works Law).
If applicable, a statement to the
affect that attendance of a pre-bid conference is a mandatory
prerequisite for bidding.
C. PRE-BID CONFERENCE
A pre-bid conference to answer questions and allow
clarifications of issues is highly recommended by the ABC. The
conference should be held well in advance of the bid date in order to
provide ample time to issue addenda responding to questions raised
during the conference. If the Awarding Authority wishes to make
attendance of the pre-bid conference a mandatory prerequisite for prime
contractors to bid on the project, this requirement must be stated in
the Advertisement for Bids.
D. RECEIPT and OPENING of BIDS
Bids must be received at the location, date and time
stated in the Advertisement for Bids or at a location, date, and time
subsequently stated in a published addendum to the bid documents. No
bids shall be received after the designated time. All bids shall be
opened and read publicly.
Bidders must follow all requirements
of the Instructions to Bidders or risk disqualification of their bid.
Any discrepancies observed upon opening bids shall be publicly noted at
that time. Each bidder’s compliance with the following statutory and
Commission rule requirements are the minimum elements to be verified
upon opening of bids:
1. Delivery envelope:
Title 34, Chapter 8, Code of Alabama, 1975,
requires licensing for general contracting when the cost of the work
exceeds amounts established by the State Licensing Board for General
Contractors. Under this law it is incumbent upon the design professional
and Awarding Authority to require each bidder to show evidence of this
license before bidding. In the absence of such evidence, a
bid shall not be received or considered. Therefore, the outside of the
envelope in which a bid is delivered must bear the bidder’s name and
state license number for general contracting and the envelope must be
sealed. The bid must not be received in the absence of any of these
features. The sum being bid may be changed by the bidder by writing the
change in price, over the bidder’s authorized signature, on the
envelope; however, if the sum being bid is revealed on the envelope, the
bid no longer constitutes a "sealed bid" and must not be received. No
change in price may be made after the time designated for receipt of
bids.
2. Bid Security:
Bid security must be furnished with bids in excess of $50,000.00. Bid
security shall be in the form of a bid bond (executed by a surety
company duly authorized and qualified to make such bonds in Alabama) or
a cashier’s check (drawn on an Alabama bank) payable to the Awarding
Authority. The amount of the bid security must be not less than of 5% of
the Awarding Authority’s estimated cost of the work or of the
contractor’s bid, but is not required to be more than $10,000.00. If a
bid bond is furnished in lieu of a cashier’s check, ABC Form C-4, Form
of Bid Bond, is to be used.
3. Proposal Form:
In addition to all pricing requirements, the Proposal Form should be
checked for acknowledgment of all addenda, identification of bid
security, complete legal signature, and complete identification of data
regarding the bidder’s state licensing for general contracting.
After bids have been opened, the apparent low bidder
may be determined. However, actual determination of the lowest
responsible and responsive bidder may only be made after the bids have
been tabulated, reviewed, and evaluated within the time period specified
in the Instructions for Bidders or Supplemental Instructions to Bidders.
All bids shall be made available for public review and inspection by all
bidders at the location of the bid opening for a reasonable period of
time after they are opened.
DELAYED RECEIPT OF BID ALTERNATE
PRICES: For projects with numerous bid
alternates, it may be advisable to allow the bidders to delay submission
of bid alternate prices for a short period (not to exceed two hours)
after they have submitted their base bids. This affords the bidders the
opportunity to focus on the bid alternate prices, minimizing the
tendency to include contingencies to cover errors that might be made
during pre-bid analysis. Upon their receipt at the advertised time, the
sealed base bids must remain sealed and secured in public view at the
location in which they were received. The sealed bid alternate prices
must then be received at the advertised time and each bidder's sealed
base bid and sealed bid alternate prices opened and read publicly. If
this procedure is to be utilized it must be stated in the Advertisement
for Bids.
LIST OF MAJOR SUBCONTRACTORS AND
SUPPLIERS: As stated on the Proposal Form,
each bidder "...declares that a list of all proposed major
subcontractors and suppliers will be submitted at a time subsequent to
the receipt of bids as established by the Architect in the Bidding
documents but in no event shall this time exceed twenty four (24) hours
after receipt of bids." Upon opening of bids, bidders should be reminded
of this requirement and the time by which the information is to be
provided.
E. CERTIFIED TABULATION of BIDS
After bids have been received, the design
professional shall check and tabulate all bids, certifying that the bids
were received sealed, publicly opened and read aloud at the time and
place advertised, and that it is a true and correct tabulation of all
bids received for the project. This tabulation shall be signed by the
design professional, notarized, and furnished to the Awarding Authority
and the Technical Staff. If a bid is incomplete, qualified, or bears any
condition or irregularity that may affect its responsiveness, the design
professional shall note this information on the tabulation. Form ABC B -
6 in Appendix B is a sample Certified Tabulation of Bids which can be
utilized or modified to facilitate project-specific bid requirements.
F. BID ERRORS, DISCREPANCIES, and MISTAKES
1. ERRORS AND
DISCREPANCIES IN THE PROPOSAL FORM
"In case of error in the extension of
prices in bids, the unit price will govern. In case of discrepancy
between the prices shown in the figures and in words, the words will
govern." ( ' 39-2-7, Public Works Law)
2. MISTAKES WITHIN THE BID
Inherent with the competitive bid
process is the possibility for mistakes in the bidder's estimate for the
bid. Forcing a contractor to perform under circumstances of an obvious
and significant mistake will frequently produce results that are not in
the best interest of the state. The Public Works Law, '39-2-11, permits
a low bidder discovering a mistake in its bid to seek withdrawal of its
bid without forfeiture of its bid guaranty under the following
conditions:
a. Timely Notice: The low
bidder must notify the Awarding Authority in writing, within three
working days after the opening of bids, that a mistake was made. This
notice may be given within this time frame whether or not award has been
made.
b. Substantial Mistake:
The mistake must be of such significance as to render the bid price
substantially out of proportion to the other bid prices.
c. Mathematical Error:
The mistake must be mathematical in nature due to calculation or
clerical error, an inadvertent omission, or a typographical error which
results in an erroneous sum. Mistakes of law, judgement, or opinion are
specifically excluded from this criteria.
d. Documentary Evidence:
Clear and convincing documentary evidence of the mistake must be
presented as soon as possible, but no later than three working days
after the opening of bids.
The law further stipulates that the Awarding
Authority’s decision regarding a low bidder’s request to withdraw its
bid without penalty shall be made within 10 days after receipt of the
bidder’s evidence or by the next regular meeting of the Awarding
Authority. Upon withdrawal of bid without penalty, the low bidder shall
be prohibited from (1) doing work on the project as a subcontractor or
in any other capacity and (2) bidding on the same project if it is
re-bid.
G. RETURN of BID SECURITY
"All bid guaranties, except those of
the three lowest bona fide bidders, shall be returned immediately after
bids have been checked, tabulated, and the relation of the bids
established. The bid guaranties of the three lowest bidders shall be
returned as soon as the contract bonds and the contract of the
successful bidder have been properly executed and approved. When the
award is deferred for a period of time longer than 15 days after the
opening of the bids, all bid guaranties, except those of the potentially
successful bidders, shall be returned. . ." (' 39-2-5, Public Works Law)
H. NEGOTIATIONS to REDUCE COST
Negotiations with a low bidder to reduce a project
cost when the low bid exceeds the available funds should be considered
highly unusual and generally a procedure not to be recommended. Instead,
every effort should be made in preparation of bid documents to secure
bids within the funds available by the use of bid alternates. However,
extenuating circumstances may arise under which an Awarding Authority
determines that negotiation of the low bid is in the public interest to
avoid delay and added costs associated with redesigning and rebidding a
project.
When considering negotiation of the low bid, the
Awarding Authority should be prepared to thoroughly document a shortage
of funding, that the negotiated changes and prices are in the public
interest and do not materially alter the original scope and nature of
the project, that time is of essence, and that no collusion, fraud, or
unjust enrichment is evidenced by the negotiations. The Awarding
Authority and its legal advisor should consider guidelines for such
negotiations as contained in a June 15, 1979, opinion of the Attorney
General. The Awarding Authority must also recognize that the Technical
Staff’s approval of a contract resulting from negotiating the low bid
does not certify its legality as this responsibility rests with the
Awarding Authority and its legal advisor.
I. RETENTION of PROPOSAL FORMS
The Awarding Authority must keep a permanent record
of the original bid proposals, the proposal envelopes with any changes
in bid prices, and in general all documents pertaining to the bids
received and the award of a contract. These records shall be open to
public inspection.
J. DETERMINATION of the LOWEST RESPONSIBLE
and RESPONSIVE BIDDER
"The contract shall be awarded to the lowest
responsible and responsive bidder, unless the Awarding Authority finds
that all bids are unreasonable or that it is not to the interest of the
Awarding Authority to accept any of the bids..." ( ' 39-2-6(a), Public
Works Law) "Proposals may be rejected if they contain any omissions,
alterations of forms, additions not called for, conditional bids,
alternate bids not called for, incomplete bids, erasures, or
irregularities of any kind. However, the Awarding Authority may reject
any and all proposals or waive technical errors if, in its judgement,
the best interests of the Awarding Authority will be promoted." (ABC
Rule 170-X-5-.06)
Through the Certified Tabulation of Bids the design
professional is required to record the relationship of the bids and any
bid conditions or irregularities that may affect the responsiveness of
any proposal. The final responsibility of determining the lowest
responsible and responsive bidder rests with the Awarding Authority.
1. DETERMINATION OF THE LOWEST BIDDER
When bid alternates are used, the method defined in
"Determination of Low Bidder by Use of Alternates" in the Instructions
to Bidders must be followed exactly. Where all, or part(s), of the
planned work is bid on a unit price basis, both the unit prices and the
extensions of the unit prices constitute a basis of determining the
lowest bidder. In cases of error in the extension of prices of bids, the
unit price will govern. Unit prices for application to potential changes
in the work are not a basis for determining the lowest bidder.
2. DETERMINATION OF THE LOWEST RESPONSIVE BIDDER
As defined by Public Works Law '39-2-6, "A responsive
bidder is one who submits a bid that complies with the terms and
conditions of the invitation to bids. Minor irregularities in the bid
shall not defeat responsiveness."
Upon receipt of the Certified Tabulation of Bids and
bid proposals from the design professional, the Awarding Authority must
determine whether or not the lowest bidder is responsive. If the lowest
bid is determined to be non-responsive, then this determination must be
made of the second, third, etc., lowest bidders until the lowest
responsive bidder is determined. In determining the lowest responsive
bidder, the Awarding Authority has the discretion to waive technical
errors and omissions in bid proposals; but it may not waive statutory
requirements or Commission rules.
a. A Bid Must Be
Rejected If:
(1) It does
not bear the full, legal description of the bidder as required on pages
1 and 2 of the Proposal Form.
(2) It is
not submitted with the required bid security.
(3) It
does not bear an authorized signature of the bidder.
(4) It is
for more than the amount requiring licensing pursuant to Title 34,
Chapter 8, Code of Alabama, 1975 and does not bear
the information regarding the bidder’s state license for general
contracting as required on page 2 of the Proposal Form.
b. A Bid May Be Rejected If:
(1) It
contains any omissions, alterations of forms, additions not called for,
conditional bids, alternate bids not called for, incomplete bids,
erasures, or irregularities of any kind.
(2) All,
or part(s), of the planned work is bid on a unit price basis and any of
the unit prices are obviously unbalanced or non-competitive. This does
not apply to unit prices requested for application to change orders,
which may be rejected without rejecting the entire bid.
3. DETERMINATION OF RESPONSIBLE BIDDER
As defined by Public Works Law '39-2-6, "A
responsible bidder is one who, among other qualities determined
necessary for performance, is competent, experienced, and financially
able to perform the contract."
The Awarding Authority must determine
which is the lowest responsible and responsive bidder by verifying
whether or not the lowest responsive bidder is properly licensed by the
State Licensing Board for General Contractors and is otherwise a
"responsible bidder". Bidders prequalified to bid pursuant to
prequalification procedures and criteria published by the Awarding
Authority are deemed "responsible bidders" (see Chapter 5, Section D.6).
If the lowest responsive bidder is found not to be responsible, the
Awarding Authority may then consider the second, third, etc., lowest
responsive bidders to determine the lowest responsible and responsive
bidder. Upon any reasonable cause, the Awarding Authority has the right
to reject any or all bids.
K. DISQUALIFICATION of BIDDERS
Any bidder(s) may be disqualified from consideration
for contract award for the following reasons:
1. COLLUSION
(Public Works Law '39-2-6)
"Any agreement or collusion among bidders or
prospective bidders in restraint of freedom of competition to bid at a
fixed price or to refrain from bidding or otherwise shall render the
bids void and shall cause the bidders or prospective bidders to be
disqualified from submitting further bids to the Awarding Authority on
future lettings."
2. ADVANCE DISCLOSURE
(Public Works Law '39-2-6)
"Any disclosure in advance of the terms of a bid
submitted in response to an advertisement for bids shall render the
proceedings void and require advertisement and award anew."
3. FAILURE TO SETTLE OTHER CONTRACTS
(ABC Rule 170-X-5-.07)
The Awarding Authority may reject a
proposal from a bidder who has not paid, or satisfactorily settled, all
bills due for labor and material on other contracts in force at the time
of letting.
L. AWARD of CONTRACT
The notice of award of a contract should state the
amount for which the contract is to be awarded, clarifying which bid
alternates are to be included, if any, and it should address acceptance,
rejection, and/or negotiation of unit prices. The Public Works Law
addresses the award of contracts under the following possible
conditions:
1. NORMAL CONDITIONS
The successful bidder is to be
notified by telegram, confirmed facsimile, or letter to the address
shown on the bidder’s proposal at the earliest possible date. (' 39-2-6)
2. DELAYED AWARD
"Should no award be made within 30 days after the
opening of the bids, or such other time as specified in the bid
documents, all bids shall be rejected and all guaranties returned,
except for any potentially successful bidder that agrees in writing to a
stipulated extension in time for consideration of its bid, in which case
the Awarding Authority may permit the potentially successful bidder to
substitute a satisfactory bidder's bond for the cashier’s check
submitted with its bid as bid security." (' 39-2-5)
3. ONLY ONE OR NO BIDS RECEIVED
"If no bids or only one bid is received at the time
stated in the advertisement for bids, the Awarding Authority may
advertise for and seek other competitive bids, or the Awarding Authority
may direct that the work shall be done by force account under its
direction and control or ... the Awarding Authority may negotiate for
the work through the receipt of informal bids not subject to the
requirements of this section. Where only one responsible and responsive
bid has been received, any negotiation for the work shall be for a price
lower than that bid." ( ' 39-2-6 )
"Force Account Work"
is defined by '39-2-1 to mean: "Work paid for by reimbursing for the
actual costs for labor, materials, and equipment usage incurred in the
performance of the work, as directed, including a percentage for
overhead and profit, where appropriate."
4. ALL BIDS ARE UNREASONABLE
"If the Awarding Authority finds that all bids
received are unreasonable or that it is not to the interest of the
Awarding Authority to accept any of the bids, the Awarding Authority may
direct that the work shall be done by force account under its direction
and control." ( ' 39-2-6 )
5. WORK BY NEGOTIATION OR FORCE ACCOUNT
"On any construction project on which
the Awarding Authority has prepared plans and specifications, received
bids, and which has determined to do by force account or by negotiation,
the Awarding Authority shall make available the plans and
specifications, an itemized estimate of cost, and any informal bids for
review by the Department of Examiners of Public Accounts and, upon
completion of the project by the Awarding Authority, the final total
costs together with an itemized list of cost of any and all changes made
in the original plans and specifications shall also be made available
for review by the Department of Examiners of Public Accounts.
Furthermore, the above described information shall be made public by the
Awarding Authority upon request. Upon the approval of the Awarding
Authority, its duly authorized officer or officers may, when proceeding
upon the basis of force account, let any subdivision or unit of work by
contract on informal bids." ( ' 39-2-6 )
M. PROJECTS COSTING less than $50,000
Under the Public Works Law, if the
cost of a public works project is less than $50,000, certain provisions
of that law are waived as follows:
1. Advertisement for Bids:
An Awarding Authority may let contracts for public works
involving $50,000 or less with or without advertising. '39-2-2(c)
2. Sealed Bids: An
Awarding Authority may let contracts for public works involving $50,000
or less with or without sealed bids. '39-2-2(c)
3. Performance and Payment
Bonds: Performance and
Payment Bonds are not required for contracts in an amount less than
$50,000. '39-1-1(e)
4. Advertisement for Completion:
For contracts of less then $50,000, the
governing body of the contracting agency, to expedite final payment,
shall cause notice of final completion of the contract to be published
one time in a newspaper of general circulation, published in the county
of the contracting agency and shall post notice of final completion on
the agency’s bulletin board for one week, and shall require the
contractor to certify under oath that all bills have been paid in full.
Final settlement with the contractor may be made at any time after the
notice has been posted for one entire week. '39-1-1(g)
Although a formal, competitive bid
process is not required by state law for public works projects costing
less than $50,000, the Alabama Building Commission recommends soliciting
at least three informal bids for such projects to assure that fair and
reasonable prices are being paid.
|