THESE
PROJECTS REQUIRE FULL PLAN AND SPECIFICATION REVIEW IN ACCORDANCE WITH
CHAPTER 3. USE ABC Form B-1: TRANSMITTAL OF PLANS AND/OR
SPECIFICATIONS, WHEN SUBMITTING DESIGN DOCUMENTS FOR REVIEW.
-
THESE PROJECTS
ARE NOT ADMINISTERED BY THE ABC; THEREFORE, THE REQUIREMENTS AND
PROCEDURES OF CHAPTERS 4, 5, 6, AND 7 DO NOT APPLY UNLESS
ADOPTED BY THE INSTITUTION.
-
THE ABC MAY
PROVIDE INSPECTIONS. THE ABC's
ROLE IN THE PROJECT SHOULD BE VERIFIED WITH THE INSTITUTION. IF SO
INSTRUCTED BY THE INSTITUTION, USE ABC Form B-10, STATEMENT of
FIELD OBSERVATIONS, AND FOLLOW THE REQUIREMENTS AND PROCEDURES OF
CHAPTER 8.
-
UNIFORM
DOCUMENTS AND STANDARD FORMS: EXCEPT AS STATED ABOVE, USE UNIFORM
DOCUMENTS AND STANDARD FORMS AS DEEMED APPROPRIATE BY THE INSTITUTION
FOR DESIGN PROFESSIONAL SERVICES, PROJECT MANUAL, AND CONSTRUCTION
CONTRACT. OCCASIONALLY, INSTITUTIONS ELECT TO UTILIZE ABC STANDARD
FORMS; HOWEVER, WHEN UTILIZING ABC STANDARD FORMS INSTITUTIONS MUST
MODIFY REFERENCES TO "DIRECTOR" (TECHNICAL STAFF, OF THE STATE
BUILDING COMMISSION) CONTAINED IN SUCH STANDARD FORMS AS CONTRACTS,
GENERAL CONDITIONS, BONDS, ETC., UNLESS THE DIRECTOR HAS AGREED TO
SERVE IN THE ROLE DEFINED BY SUCH REFERENCES.
1. Submit original documents - no carbon copies.
2. Do not highlight text. Highlighted text does not produce a good
scanned image.
3. Preferably, submit only letter size (8 2
X 11) documents.
4. Preferably, send only one-sided documents.
TYPICAL ROUTING OF DESIGN DOCUMENTS DURING PLAN
REVIEW
All
submissions of design documents must be transmitted using
ABC Form B-1,
TRANSMITTAL of PLANS and/or SPECIFICATIONS.
1. DESIGN PROFESSIONAL
a. PREPARES DESIGN DOCUMENTS (SCHEMATIC)
(PRELIMINARY) (FINAL)
b. REVIEWS EACH LEVEL OF DESIGN WITH INSTITUTION FOR
APPROVAL
c. SUBMITS EACH LEVEL OF DESIGN TO ABC FOR REVIEW AND
APPROVAL
d. SUBMITS "FINAL" DESIGN TO OTHER REVIEWING AGENCIES
(DEPT. OF PUBLIC HEALTH, etc.) CONCURRENTLY WITH SUBMISSION TO ABC
2. ALABAMA BUILDING COMMISSION
a. REVIEWS EACH LEVEL OF DESIGN FOR COMPLIANCE WITH
BUILDING CODES AND ABC REQUIREMENTS
b. CONFIRMS APPROVAL OR REJECTION WITH A "PROJECT
COMMENT LETTER" TO THE DESIGN PROFESSIONAL AND INSTITUTION
c. RETAINS SCHEMATIC & PRELIMINARY SUBMISSIONS UNTIL
FINAL SUBMISSION IS APPROVED; RETAINS APPROVED FINAL SUBMISSION AS A
PART OF THE PROJECT RECORD
3. DESIGN PROFESSIONAL
a. ADDRESSES REVIEW COMMENTS BY ABC, ADVANCING TO THE
NEXT LEVEL OF DESIGN UNTIL APPROVAL OF FINAL SUBMISSION IS OBTAINED
b. UPON OBTAINING APPROVAL OF FINAL SUBMISSION
FOLLOWS INSTITUTION'S PROCEDURES FOR ADVERTISING AND RECEIVING BIDS.
|